Key Milestones

2023
March
Project Kickoff
2023
Spring - Fall
Preliminary Surveying and Engineering
2023-2024
Winter - Summer
Develop Preliminary Design
2024
Winter
First Public Meeting and Comment Period
2024
Winter - Summer
Refinement of Preliminary Engineering Concept
2024
Summer - Fall
In-person Public Meeting on Sept. 17, 2024, from 6–8 p.m. and Public Comment Period from Sept. 17 through Oct. 18, 2024
2024-2025

Evaluate Public Comments, NMDOT Reviews, and Federal Reviews
2026
Release Request for Proposals to Potential Design-Builder Contractors for Bidding
​
Award Selected Design-Build Contractor
2027
Develop Final Design
​
Anticipated Start of Construction